Street Program Schedule

If you have any questions please call the Streets Department at (610) 437-7638

Schedule is subject to change and weather dependent

 

WEEK OF MAY 16 TO MAY 20


Monday

  • Miscellaneous Street Work
  • 9.5MM Slips
  • 25 MM slips
  • Leveling- N Filbert St ( Hamilton - Walnut St)
  • Mill- Walnut St (Halstead - inn St)
  • Potholes City Wide

Tuesday  

  • Miscellaneous Street Work
  • Mill- Halstead St ( Hamilton - Walnut St)
  • Crackseal
  • 9.5 MM Slips
  • 25 MM Slips
  • Potholes City Wide

Wednesday

  • Miscellaneous Street Work
  • 25 MM Slips
  • Mill- Fenwick St ( Cedar St - Highland St)
  • Potholes City Wide
  • Sawcutting 

Thursday    

  • Miscellaneous Street Work
  • Crack sealing
  • Mill- Fenwick St ( Cedar St - Highland St)
  • 9.5 MM Slips
  • 25 MM Slips
  • Potholes City Wide

Friday  

  • Miscellaneous Street Work
  • Potholes City Wide
  • Mill- Fenwick St ( Cedar St - Highland St)
  • 9.5MM Slips
  • 25 MM Slips
  • Crackseal
  • Saw Cuts