Street Program Schedule

If you have any questions please call the Streets Department at (610) 437-7638

Schedule is subject to change and weather dependent

 

WEEK OF  JUNE 5 - JUNE 9


Monday

  • Miscellaneous Street Work
  • Potholes - Citywide
  • LCA - Curb Back Ups
  • Milling - Bryan St (Allen - Gordon St)
  • Overlay - SW 30th St (Emmaus Ave - Ithica St)
  • 25mm/9.5mm

 

Tuesday  

  • Miscellaneous Street Work
  • Potholes - Citywide
  • LCA - Curb Back Ups
  • 25mm/9.5mm
  • Milling - Bryan St (Allen - Gordon St)
  • Overlay - SW 30th St (Emmaus Ave - Ithica St)

 

Wednesday

  • Miscellaneous Street Work
  • Potholes - Citywide
  • LCA - Curb Back Ups
  • 25mm/9.5mm
  • Milling - 2nd St (Tilghman St - Green St
  • Leveling - SW 28th St

 

Thursday    

  • Miscellaneous Street Work
  • Potholes - Citywide
  • LCA - Curb Back Ups
  • 25mm/9.5mm
  • Milling - Brush St (Bryan - 3rd St)
  • Overlay - SW 28th St

 

Friday  

  • Miscellaneous Street Work
  • Potholes - Citywide
  • LCA - Curb Back Ups
  • 25mm/9.5mm
  • Milling - Clean up and maintenance