The following schedule outlines the planned phases for the Realignment and Center Square Project. All dates are subject to change based on weather and field conditions.
Pre-Construction Activities
- April 20 – April 24, 2026
Site preparation, mobilization, layout, and exploratory pipe locating.
Construction Phases
- Phase 1 – NW Corner (PPL Center)
April 27 – May 21, 2026
- Phase 2 – SW Corner (702 Hamilton St)
May 21 – June 12, 2026
- Phase 3 – NE Corner (2 City Center / 645 Hamilton St)
June 10 – August 5, 2026
- Phase 5 – Linden St & 7th St (West Corners)
July 15 – August 7, 2026
- Phase 4 – SE Corner (County Building and Vault)
July 31 – October 5, 2026
- Phase 6 – Final Paving (Full Project Length)
September 22 – November 6, 2026
Hamilton Street Streetscape (600–700 Block)
- Start Date: May 11, 2026
- Duration: Approximately 70 working days
This work will be coordinated with the realignment and plaza improvements to maintain consistent traffic patterns.
Traffic Closures and Impacts
Hours: Monday through Friday, 8:00 AM – 4:00 PM
- Lane and parking restrictions will be in place throughout the duration of the project.
- Additional updates will be provided as each phase progresses.
April 20 – April 24, 2026
- Traffic controlled by flaggers
- No full lane closures anticipated
Phase 1 – Lane Closures
- Hamilton Street:
South lane closure westbound from 7th Street (in front of the PPL Center)
- 7th Street:
West lane closure southbound through the Hamilton Street intersection